Importaco logo
Food · Process heat · Turnkey

Importaco Valencia: solar process heat from the roof

≈ 325 kWtinstalled thermal power
634 m²of mirrors on a sloping roof
Turnkeybusiness model (plant purchase)
2022/2026commercial operation date (COD)
High temperatureprocess heat
The original plant (2022), layer by layer · schematic model
Pitched roof at Importaco with the first blue anchors
Blue anchors on the roof
Blue steel rail structure installed on the roof
Rail structure, installed
A module slides along the rails (sped-up video)
Aerial view of the Importaco Fresnel field operating on the roof
The plant operating on the roof
Loading the 3D model…Drag to rotate
The challenge
Bring solar heat to the factory process without using any land. The only surface available was the building’s pitched roof, surrounded by other buildings, and the plant had to fit into the existing heat circuit without changing how the boiler operates.
The solution
An FLT20 field of 8 tandems in two rows, with 634 m² of mirrors, on a rail structure anchored to the roof. The modules arrived pre-assembled and slid along the rails into position. The field heats the fluid returning from the process before it reaches the boiler, with no storage.
Business model
A turnkey project commissioned in 2022 and rebuilt in 2026 after damage caused by the 2024 DANA storm.
Importaco Fresnel field on the factory roof
The original plant, in operation since 2022.
Rebuilt Importaco Fresnel field
The renewed plant, in 2026.
How the plant worksFour operating modes, from start-up to night. Tap to see the animation.